Motor Mill Bridge Project Timetable

  • Steel has been ordered with delivery the week after Labor Day.  Mobilization will begin September 10th.
  • Clearing and grubbing, temporary bridge, cofferdam installed.
  • Tuckpointing and Pier repair, pier cap, abut caps and abutment wings installed completed by October 22
  • Bridge Assembly completed by November 12
  • Set trusses completed by November 14
  • Decking and railing installed completed by November 28th
  • Final approach work, site restoration and final walk through December 5th.