Motor Mill Bridge Budget

At the May 8, 2012 Clayton County Conservation Board meeting the board approved the low bid for the bridge project to Minnowa Construction from Harmony MN for $906,322.

The steel for the bridge has been ordered and work will be started in early fall of 2012.

The Motor Mill Foundation continues to raise funds for the remaining $90,000. Your support is appreciated.

Motor Mill Bridge Budget
 Expenses
 Abutment, Pier and Bridge Construction  $  906,322
 Engineering  $  142,000
 Construction inspection  $    21,000
 Estimated Total   Expenses                    $1,069,322
 Funding Sources                                  Secured
FEMA  $ 432,427
 REAP  $  463,000
 UMGC  $  20,000
 Great Places  $   33,000
 Construction inspection by County Engineer office  $  11,000
 Capital Fund Campaign  $  22,845
 TOTAL                $978,089
  Remaining Needed Dollars as of 8/30/2012      $  87,050

 View the plans!

Motor Mill Bridge ProjectDonations can be sent to:

Motor Mill Foundation
29862 Osborne Rd
Elkader IA 52043

OR

Clayton County Conservation
29862 Osborne Rd
Elkader IA 52043

Donations to the Motor Mill Foundation, a 501c3 organization, or the Clayton County Conservation Board are 100% tax deductible.

Leave a Comment

Scroll to Top